Exciting progress has been made inside and outside the athletic building during January and February. The roof installation is underway, exterior siding installed and the concrete mezzanine complete on the south side overlooking the Knights soccer field.
Inside on the ground level, metal beams outline the concession stand, team locker rooms, visitor restrooms and a dance studio/multipurpose space. The front entrance of the building will include a lobby, elevator and staircase leading to the second floor. On the second floor, work is beginning on the putting green and golfing bays along the north wall. A large viewing windows will overlook the soccer field, with a smaller press box next door.
The path of the second driveway is complete, leading to the middle school circle drive and parking lot. Curbs and gutters are complete; the first layer of asphalt is installed. The top layer will be poured in the spring.